Building inspection types
Foundations and Substructure
Siting and Foundations
Confirms the building is correctly positioned on site in accordance with approved plans, including boundary setbacks, levels, and orientation. Also verifies excavation depth, bearing capacity, and foundation preparation prior to construction.
Sub-floor Framing
Ensures piles, footings, bearers, joists, fixings, and ventilation meet structural and durability requirements before flooring systems are installed.
Underslab Services
Verifies reinforcing steel, mesh placement, vapour barriers, edge thickening, and service penetrations comply with approved documentation before the concrete pour.
Structural and Framing
Framing Skeleton
Inspection of wall framing, lintels, beams, trusses, and roof structure to ensure correct sizes, spacing, bracing, and fixings are installed as per plans.
Post Line Rigid Air Barrier Bracing
Confirms rigid air barrier systems and associated fixings are correctly installed to provide both structural bracing and weather-tightness performance.
Blockwork
Assesses masonry construction including block placement, reinforcing steel, grout fill, control joints, and workmanship to ensure structural integrity.
Half-height Masonry
Inspection of masonry walls at an intermediate stage to verify reinforcing and construction quality before further height is added.
Building Envelope
Pre-cladding - Wrap/Cavity
Checks building wrap, flashing tapes, cavity systems, and penetrations are correctly installed to prevent moisture ingress prior to cladding installation.
Pre-line Inspections
Pre-line Building
Confirms insulation, structural elements, and general building components are installed correctly before interior linings are applied.
Pre-line Plumbing
Checks plumbing pipework layout, support, pressure testing, and compliance before walls and ceilings are closed in.
Pre-line Combined
A coordinated inspection covering both building and plumbing elements at preline stage to streamline the process and reduce delays.
Post-line Inspections
Post-line Fire Rating
Ensures fire-rated walls, ceilings, and penetrations meet specified fire resistance levels after installation of linings.
Post-line Interior Linings
Checks plasterboard and other linings are installed correctly with appropriate fixing patterns before stopping and finishing.
Wet Area Membrane
Verifies waterproofing systems in wet areas are applied correctly, including substrate preparation, membrane coverage, and detailing before tiling or finishes.
Services and Drainage
Foul and Stormwater Drainage
Inspection of drainage systems including pipe gradients, connections, bedding, and testing to confirm compliance before backfilling.
Effluent Field First Inspection (Trench)
Checks on-site wastewater disposal systems including trenching and materials to ensure environmental compliance.
Effluent Field Second Inspection (Commissioning)
Checks on-site wastewater disposal systems including Pump Chambers, distribution i.e. Flow testing and materials to ensure environmental compliance.
Solid Fuel Heating Appliance
Free Standing Appliance
Verifies installation of heating appliances, flues, and clearances to ensure safety, ventilation, and compliance with manufacturer specifications for a Free Standing Appliance.
Insert Appliance First Inspection
An Insert refers to an installation in a Masonry cavity. The first inspection is to check and confirm that the cavity is ready for an appliance to be installed.
Insert Appliance Second Inspection
An Insert refers to an installation in a Masonry cavity. The second inspection is to check and confirm heating appliances, flues, and clearances to ensure safety and compliance with manufacturer specifications
In-built Appliance First Inspection
An In-built refers to an installation in a Timber Framed Cavity. The first inspection is to check and confirm that the cavity is ready for an appliance to be installed including any clearances to combustibles and venting requirements.
In-built Appliance Second Inspection
An In-built refers to an installation in a Timber Framed Cavity. The second inspection is to check and confirm heating appliances, flues, and clearances to ensure safety and compliance with manufacturer specifications
Liquid Fuel Appliance
Verifies installation of heating appliances fueled by liquid fuel e.g., Diesel, Biofuels and includes checking of flues, and clearances to ensure safety, ventilation, and compliance with manufacturer specifications for a Free Standing Appliance.
Specialised Inspections
Swimming Pools
Inspection of pool structure, fencing, gates, and barriers to ensure safety and compliance with pool regulations.
Minor Variation
Assessment of proposed changes to approved consented plans to determine whether they remain compliant with Building Code requirements.
Amusement Devices
An inspection based around the safe operation of an amusement device which is a mechanically powered unit that is used for entertainment, e.g. merry-go-rounds, Ferris wheels, go-karts and minibikes, etc.
Dangerous and Insanitary
This is an inspection carried out to identify, assess, and manage buildings that pose a risk to people’s health or safety.
Final and Certification
Final Residential Building
Comprehensive final inspection confirming all building work is completed in accordance with consented plans and Building Code requirements.
Final Commercial Building
Final inspection of commercial projects including accessibility, fire safety systems, and specified systems compliance.
Final Accessory Building
The final inspection confirming all building work in conjunction with an accessory building e.g., garage is completed in accordance with consented plans and Building Code requirements.
Certificate of Public Use (CPU)
Inspection to confirm that a building or part of a building is safe for public use prior to the issue of a Code Compliance Certificate.