Specified systems
Application and issuing of the Building Consent
Performance Standards must be consistent across all documentation, e.g., the plans and specifications must reflect the Fire Report.
You will need to specify on the Form 2 Application one of the following for each system
- Existing Specified System
- New – Added to existing Compliance Schedule
- Altered Only – No change to existing Compliance Schedule details
- Changed – Compliance Schedule details require amendment
- New – New Compliance Schedule being created
- Removed – Existing Specified System being remove
Once the application has been formally received it will be sent to our processing team for a technical review. Any further information requests will be sent via the Objective Build portal.
Specified Systems and Performance Standards will be listed on the Building Consent (Form 5).